We thought the construction of the State/Obernuefemann Roundabout would begin this week, but so far the contractor is missing in action. We have been told that they now plan to begin working on Monday, April 21. As before, please take special care when driving through the construction zone and take alternate routes whenever possible.
In contrast, the contractor for the asphalt paving program started early and is going strong. As a result, the paving schedule has been modified:
April 15-22: East Jefferson and Park Entrance
April 21-25: Sunnyside, Center Grove, Countryside, Hillcrest, Mill, Wintergreen, and Rain Hollow
April 28-May 2: Walnut, Nancy, Griffin Gate, Aladar, Amy, Affirm, Thomas, Colleen, and Donna
May 5-13: Edna, Agnes, Annice, Lakewood, Melissa, and Shoreline
|  |